Projects
2005
Projects
2004
Projects
2002
Projects
1996-2001
Client
List
       

PROJECTS - 2003

       

18 December 2003
Altaca have prepared for
Schlumberger design concepts for their proposed Lift Manufacturing - Assembly - Testing Facility to be constructed in Russia. 

 

   


09 December 2003
Following a competitive tender Altaca have been appointed by
LeBoeuf, Lamb, Greene & MacRae LLP, a leading law firm, to carry out the renovation and fit-out of office space adjoining their existing offices located on Nikitsky Pereulok in the centre of Moscow. Altaca undertook a previous project for the same company 6 years ago. The architects, who will also act as the Project Managers, are Murray O'Laoire.

 


03 December 2003
The
Anglo-American School, following our successful completion of a major fit-out project for them this Summer, have appointed Altaca to undertake the complete design and construction of  acoustic and allied works in several areas of the school including the dining areas, kitchen, theatre and music rooms. The work is to commence at the start of the school's Christmas and New Year holidays and is to be completed in 3 weeks.
 


27 October 2003
Baker Hughes
have appointed us to undertake additional fit-out work at their new offices in Aerostar Place. This follows the successful completion of the initial fit-out project that we completed at the end of July 2003. This expansion is due to be completed within 1 month.
 

22 September 2003
Following a competitive tender we have been appointed by
Deloitte to undertake the fit-out of additional space in their offices located in the Mokhovaya Business Centre. The project is due to start commence on-site on November 10th with completion in 5 weeks.

Altaca have previously undertaken two previous office fit-out projects for Deloitte.
 


18 August 2003
The
Anglo-American School today started their 2003/4 academic year and occupied the new facilities constructed by Altaca during their Summer break. Over 1,500m2 of shell & core space was converted into classrooms, theatre, computer rooms, staffrooms, pe & exercise areas and other facilities in 7 weeks by an Altaca team of over 150 staff.


31 July 2003
Baker Hughes today took over occupancy of their new offices located in Aerostar Place on Leningradsky Prospect. The project was awarded to Altaca (on a negotiated contract basis) in January of this year, work started on site at the beginning of May and the fit-out of over 1,400m2 was completed in 13 weeks.


09 July 2003
We have been awarded a contract by a
private client to construct a luxury country residence located in the village of Zukovka close to Rubelovskoe-Uspenskoe Schosse to the West of Moscow. The house has been designed by Smiros & Smiros Architects of New York with detailed design by Murray O'Laoire in Moscow (who will also act as the client's Project Manager). The engineering concept design is by Ove Arup. The project has started immediately and is due for completion in 15 months.
Altaca will be responsible for carrying out all detailed engineering design work for the project.



26 May 2003
We have been engaged by the
Anglo-American School in Moscow to convert attic and basement areas totaling over 1,500m2 into classrooms, a theatre, a music room, computer area, exercise room and storage area. The design-build fast track project will commence on-site on the 6th June and is scheduled for completion by the end of July, a total duration of 8 weeks. At the peak we expect to have on-site over 130 personnel. The scope of works includes civil, mechanical and electrical works including all associated design work. The contract was awarded to Altaca on a competitive tender basis. The client's Project Manager is Davis Langdon Europe.

Anglo-American School


 

01 May 2003
Work has commenced on-site for the new
Baker Hughes offices at Aerostar Place. The fit-out of the 1,440m2 is planned to be completed by the end of July. 

Aerostar Place


 

10 April 2003
Altaca have today handed over to the client,
Dandy-Stimorol-Cadbury, their new offices at the Westbridge Park Office Complex. The project, which was completed from shell and core, was undertaken on a fast-track basis and required only 7 weeks from start to finish. The scope of work included demolition of existing structure and a full civil, mechanical and electrical installation including raised floors throughout.

Westbridge Park


 

07 April 2003
Final completion has been achieved at the
Fitch Ratings offices in Ducat II, the project, which involved the fit-out of 250m2 of space, was completed from shell and core in 8 weeks from our appointment.

Ducat II


 

14 February 2003
Altaca have been appointed to carry-out the fit-out of 1,400m2 of shell and core office space in the new Westbridge Park Office Complex located on Leningradsky Prospect, work on-site will commence immediately. The client is
Dandy-Stimorol-Cadbury and their Project Manager is Time-CC. The project is to be completed on a fast-track basis with the client taking occupation within 7 weeks from project commencement.

 


28 January 2003
We have been appointed, following a competitive tender, to undertake the design-build fit-out of
Fitch Ratings new offices to be located in the Ducat II Office Centre on Ulitsa Gasheka. The premises, comprising 250m2, are in shell & core condition and will be fitted out to A-class standards.

 


23 January 2003
Altaca have been appointed by
Baker Hughes to undertake the fit-out of their new offices which are to be located in the Aerostar Place Office Centre on Leningradsky Prospect in Moscow. The offices will be on the 4th and 5th floors and total 1,440m2 of previously occupied space. The project is to be completed to a concept design prepared by the Houston-based architect Kirksey. The contract was awarded following interviews with the client and is on a negotiated contract basis. On-site work is planned to start at the beginning of May with hand-over to the client due for the end of July.

 


06 January 2003
The World Bank
have today completed the relocation into their new offices located at Bolshaya Moltchanovka 36. The 5,000m2 fit-out project was completed 3 weeks ahead of the contracted completion date.

 

 

Open Society Deloitte & Touche Stimoral-Dandy Renaissance Capital Bank of America
 
Home | Overview | Projects | Contact Us